The project will consist of 200 wind turbines, each with a capacity of 4 megawatts (mw). each turbine costs
$1.2 million to build. electrical demand in the area to be served by the project is expected to be 2.0 x 100 mwh
per year.
(d) calculate how much electricity (in mwh) the wind project needs to generate per year in order to provide
80% of the annual electrical demand in the service area. show all work.
(e) customers in the service area pay $0.20/kwh for electricity. calculate how much revenue will be produced
if the wind turbines provide 80% of the annual electrical demand in the service area. show all work.
(f) assuming all turbines are operating, calculate how many hours the wind turbines must operate to provide
80% of the annual electrical demand in the service area. show all work.

ansver
Answers: 3

Another question on Advanced Placement (AP)

question
Advanced Placement (AP), 25.06.2019 20:00
In 2009, florida suffered more fatalities than any other state. a. bicyclist b. child passenger c. pedestrian d. impaired driving
Answers: 1
question
Advanced Placement (AP), 26.06.2019 01:40
Abdid is an astronomer who has been observing objects that orbit the sun in the asteroid belt. he finds a previously undiscovered round, rocky object that is not similar in shape to the rest of the asteroids. what has abdid most likely found?
Answers: 1
question
Advanced Placement (AP), 26.06.2019 13:50
Ahummingbird travels from plant to plant to feed itself. which of the following ecosystem services does this hummingbird most likely provide? i. pollination ii. seed dispersal iii. soil preservation i only ii only iii only i and ii only ii and iii only
Answers: 2
question
Advanced Placement (AP), 27.06.2019 00:30
Submitting the profile which includes sending a report to one college cost
Answers: 2
You know the right answer?
The project will consist of 200 wind turbines, each with a capacity of 4 megawatts (mw). each turbin...
Questions
question
Mathematics, 03.08.2019 19:00
Questions on the website: 13722363